It is the responsibility of the Owner to ensure their contractors, employees, and suppliers are aware of and follow all rules while within the Subdivision.
Section 5.01 Requirements During Construction
a. No loud music shall be allowed.
b. The burning of brush, trees, or construction materials is not allowed in the Subdivision.
c. The worksite must be kept neat and clean.
d. Proper storage containers for debris must be present from delivery of any material to the job site until project completion. For new home construction and major construction projects, a dumpster or other portable debris receptacle is required. No onsite built trash receptacle is allowed.
e. The Owner/Contractor shall pick up trash daily.
f. All trash shall be kept off the roads and adjoining property at all times.
g. Loose or uncovered trash shall not be hauled through the Subdivision.
h. Construction materials shall not be placed in Association trash/garbage dumpsters or debris areas. All construction debris must be removed from Westwood Shores.
i. No construction materials may be located within 5 feet of the roadway or on adjacent property unless waived in writing by ACC. Waiver requests must be made at the time of application.
j. At least 1 portable toilet must be supplied for each new home construction site when a project will require more than 1 day. This toilet must be onsite before any construction can begin. An exception may be granted on additions and/or remodeling if the Owner allows the use of existing facilities.
k. Portable toilets should be at least 15’ off the road unless waived by ACC and serviced on a regular basis.
l. All posted speed limits must be obeyed.
m. Cleaning and/or dumping excess concrete is not allowed in Common Areas, including streets and roads. Concrete trucks shall raise their chute before leaving the job site so no concrete will be dropped on the road.
n. “Wash out and retention area” is required for all concrete pourings. Retention area must have 6 mil polyurethane liner.